The Woods of Mt. Oak

As we come out of winter and towards the completion of the project, we work hard to complete the exterior and the interior at the same time with multiple crews.

DSCN0249

The kitchen is almost completed and the
various lighting aspects are looking really good.

DSCN0255

The fireplace in the great room is a true work of art
and very unusual with its multiple mantles.

DSCN0258

The basement is almost finished and its a party area for sure. The floors are polished, the bar is done, and the four sided fireplace is the only one in the region.

DSCN0271

Mediterranean On The Potomac

As we move the the project into drywall, we perform a series of
frame checks to insure quality in the rough framing.

DSCN0299

The stairs were custom made for the project and have now been set.

DSCN0302

Here in the basement we have prepped the swimming pool that will be in the basement and installed various pieces of equipment. Moisture is our biggest concern in a project such as this and the way we manage it is very important

DSCN0313

The Woods Of Mt. Oak

Here you can see some pictures of the roof system being installed from a perspective from inside the house. The roof is a massive piece of work that is truly a work of art.

011

012

Here is an interior shot of the massive kitchen area and the 2 doors and the 2 sided fireplace area, that will be located at the end of the room.

014

The Woods of Mt. Oak

We have finally poured the foundation, it was a great day with over 20 concrete trucks and over 200 yards of concrete. This is a picture of the pump truck getting ready to pump the concrete.

651

Here is a picture of the massive amount of steel wall panels that we had to fill up with concrete to create the foundation.

633

This picture below shows you what the concrete foundation looks like once the steel forms are removed. The concrete is now curing and will reach its maximum strength in approximately 28 days. By code, we must wait a minimum of 7 days before putting dirt against the foundation.

20140312_110937

Mediterranean on the Potomac

Here you can see the massive crane that we used to set the house steel.

039

The picture below shows the massive steel beams that are set in place and ready for the floor to be installed. Some of these steel beams we are using are 18″ inches tall and this size steel beam is unheard of with typical residential construction.

042

Here you can see that the steel beams are so large that they
can not be unloaded without the help of the crane.

020 (2)

Mediterranean on the Potomac

We finally poured the concrete walls on Monday, January 27, 2014.

It was cold and windy, but because we are using insulated concrete forms, we
were able to pour the concrete walls. We covered the top of the walls with
blankets to keep the heat inside the forms. 099 - Copy

Here you can see the large pump truck that we used to pump the concrete through a large hose and into the forms.

080 - Copy

Here you can see the waterproofing membrane that we have
installed over the concrete walls.

Look at how the Potomac River is frozen in the background!

009

Here in this picture you can appreciate the thickness of these basement walls.
The walls are 17 1/4″ thick with 12″ of solid concrete.

You can huff & puff but your never going to blow this house down!

011